The project had previously stalled due to a lack of government funding.
Funded by $1.6 million in devolution funds, the project is expected to be completed within 60 days after failing to meet initial timelines. An additional $440,000 will cover the Zengeza 4 Pagomba sewer project.
For both endeavors, the Council is utilizing materials donated in 2020 by the African Development Bank.
An insider revealed that the overall cost of the initiative will reach $2 million.
“We have a total of 9.88 km worth of piping material, which we are using to rehabilitate 3.5 km from the Zengeza Outfall plant to Zengeza 5,” the source said.
“Once the project is complete, many residents will benefit, as several hotspots in Zengeza and St Mary’s will be relieved.
The combined cost, including the PaGomba project, is about $2 million across two lots of interventions.”
The source added: “The original timelines were not met due to a lack of government funding, which caused delays and led the contractor to move off-site.
However, last week the government released funds to pay off outstanding interim payment certificates, which is why the contractor is back on site. The contractor now has 60 days to complete the work.”
Posting on its official Facebook page, the Municipality of Chitungwiza indicated that the Zengeza Sewer Outfall project has reached 68% completion.
“The progress was highlighted during a two-day visit by Best Practice assessors evaluating Acting Town Clerk Mr Japson Nemuseso as part of his performance contract,” the municipality stated.
According to assessor Mr Guardiner Manika, the local authority has demonstrated significant progress.
“There is positive traction in those areas, though there is still a lot of work to be done.”
Residents from the affected neighborhoods expressed deep relief at the news.
“At least we can see some progress,” said one resident who spoke on condition of anonymity.
“Living in an environment heavily polluted with raw sewage was unbearable, especially with children. I hope the municipality continues this positive trajectory and addresses all the areas needing attention.”
Another resident, Mr Mapeto, added: “This was long overdue. Sometimes you wonder whether management realizes how bad the situation is. For now, we applaud them for the work, but much more needs to be done because we are suffering due to poor liquid waste management.”
A tour around Chitungwiza reveals that aging infrastructure remains a critical issue, with many residents still struggling with sewage overflows.
Addressing these broader infrastructural failures in earnest remains an urgent priority for the local authority.